CCPM IMPLEMENTATION

Critical Chain doesn't fail on theory. It fails on rollout. Here's how we roll it out.

A Critical Chain (CCPM) implementation with Realization changes how your organization plans, releases and runs projects, and it typically shows results within about 90 days. It starts with a baseline of your current projects and the resource that limits them. Next comes a pilot that cuts work in process and puts projects on Critical Chain schedules in Concerto. Then the rollout widens to more teams, and weekly buffer reviews keep it running. The full timeline depends on how many projects, sites and teams are involved, and we scope that with each customer. Training happens along the way, for the people who plan the work, the people who manage it and the people who do it.

What does a CCPM implementation involve?

A CCPM implementation is a change in management behavior, supported by software. It is not a software installation with some training at the end.

Most organizations already know their projects are late. Many have read Critical Chain or sat through a course. The hard part is changing what happens on Monday morning: which projects start, what people work on first, and what managers look at when they walk the floor. That's where most attempts stall, and it's what our rollouts are built around.

New to the method? Read the complete CCPM guide

Step by step: how a rollout runs

Phase

What happens

What you get

1. Baseline

We map your active projects, shared resources and where work waits longest

A clear picture of the constraint and how much work is in process

2. Pilot

One area cuts work in process, rebuilds its plans on the critical chain and starts buffer management in Concerto

Proof on your own projects

3. Rollout

More teams, sites and project types move onto one shared schedule

One set of priorities across the portfolio

4. Sustain

Weekly buffer reviews, coaching and fine-tuning until the new way of working is the normal way

Results that last after we step back

The pilot matters most. It is where your own people see projects finish faster on your own work, and that does more for adoption than any presentation.

Training for every level of the organization

Critical Chain only works when every level plays its part. Training follows the rollout, so people learn the method on their real projects, not on a case study.

Executives

Executives learn how to control work in process, set portfolio priorities once and read buffer status across all projects. Their job is to stop starting and start finishing.

Project and resource managers

Project and resource managers learn to build Critical Chain plans with focused durations and buffers, release work based on capacity, and run short buffer reviews that act on the projects in trouble.

Team members

Team members learn to work from one priority list, finish a task before starting the next and hand work over as soon as it's done, like runners in a relay.

What changes for your teams on day one

These are the visible changes once a team goes live:

1. Fewer projects in progress. Some projects pause so the others can move. It feels wrong at first.

2. One priority list per person. Nobody has to guess which project's email to answer first.

3. Shorter meetings. Reviews look at buffer status: green, yellow, red. Managers spend their time on the red projects.

4. Alerts before delays, not reports after them.

"Changing all these schedules, for aircraft lines, back shops, engineers and procurement, and keeping them synchronized within and across aircraft is humanly impossible. [...] We were also able to shift management's focus. They moved from backward looking reports to forward-looking delay and bottleneck alerts."

Sanjeev Gupta, CEO, Realization, on the US Navy F/A-18 depots

How fast do results appear?

Realization customers often see results within 90 days. A few examples, as they reported them:

Organization

How fast

What changed

National Thermal Power Corporation of India

Within a month

Complete visibility of bottlenecks; major milestones completed on time

US Navy F/A-18 depots

About four months to get the plan moving

Depot throughput up 40% within a year

Emesa, rail station construction

Six months

Completed 11 months of work in 6 months; €5M penalty avoided

"Within a month, our project management team had complete visibility of bottlenecks. Even when new bottlenecks emerged, there were no surprises."

Ajay Shukla, AGM, National Thermal Power Corporation of India

See all customer results

Partners in Europe and beyond

Realization works with implementation partners who know the method and Concerto.

CMG Consultores (Spain)

Europe's pioneer in Demand Driven MRP, with Critical Chain Project Management and Concerto implementations. Its founding partners trained at the Academy of the Goldratt Institute.

CBS

More than 13 years helping organizations cut project cycle times while keeping scope and resources fixed, often with major improvements within two months.

Partner contact details

Frequently asked questions

How long does a CCPM implementation take?

Realization customers typically see results within about 90 days. The full rollout depends on the number of projects, sites and teams, and Realization scopes it with each customer.

Do we need software to implement Critical Chain?

For a handful of projects, Critical Chain can run on spreadsheets. Organizations running many projects on shared resources need software that keeps every schedule and buffer up to date as things change. That's what Concerto does.

What is the hardest part of a CCPM rollout?

Cutting work in process. Pausing projects feels like going backwards, but starting fewer projects is what lets the rest finish faster.

How do we get started with CCPM?

Start with a conversation about your projects and where they get stuck. Realization then baselines your current portfolio and proposes a pilot.

Is this different from a CCPM training course?

Yes. A course teaches the method. An implementation changes how your projects actually run, with the training built into the rollout on your own projects.

Ready to finish more projects with the same people?

If you can live with small incremental improvements, you don't need us. If you want a rollout that sticks, let's talk.