Running ten projects isn't ten times harder than running one. It's a different problem.
Multi-project management is the planning and control of many projects that share the same people, equipment and budget. Its main risk is resource contention: when everyone works on everything at once, every project slows down. That's why priorities and start dates have to be set across the whole portfolio, not project by project. Critical Chain multi-project management does this with one shared schedule, a limit on work in process and priorities set by buffer status. Realization's multi-project software, Concerto, has run this way since 1999, when Realization became the first company to bring multi-project, web-based scheduling to the world of projects.
Most project tools treat each project as if it had the organization to itself. Each project manager plans their project, books the people they need and promises a date. Then all those plans meet the same engineers, the same test rigs and the same hangar bays.
What follows is predictable:
What happens
Why
The cost
Bad multitasking
People are assigned to several projects and switch between them
Every task takes longer, on every project
Too much work in process
Projects start as soon as they're approved, whether or not there's capacity
Work waits in queues; nothing finishes
Priority fights
Each project is "top priority" to someone
The loudest project wins, not the most important one
Hidden bottlenecks
One overloaded resource feeds many projects
The whole portfolio moves at the speed of that one resource
Adding more people rarely fixes this. To solve traffic jams, you don't add more cars to the road. You find ways to reduce their number.
The fix starts with one schedule for the whole portfolio instead of many separate ones.
In Critical Chain multi-project management, every project is planned against the same pool of shared resources. The schedule knows when a specialist is already committed elsewhere, so no plan assumes people are free when they aren't. Each project gets its own critical chain and its own project buffer, and the portfolio is staggered so the most constrained resource is never overloaded.
This is the idea Realization has worked on for 25 years. The US Patent Office granted Realization a patent for the facilitation of multi-project management using the Critical Chain methodology.
New to Critical Chain? Read the complete CCPM guideWhen every project has a buffer, priorities stop being a matter of opinion.
Buffer status
What it means
What managers do
Green
The project has used less buffer than the work it has completed
Leave it alone
Yellow
Buffer use is getting ahead of progress
Plan a recovery action
Red
The delivery date is at risk
Act now, and move resources if needed
Every person gets one task list, ranked by which tasks protect the most at-risk projects. Nobody has to guess which project's email to answer first, and executives spend their time on the few projects in red.
Starting a project early feels like getting ahead. In a multi-project environment, it usually does the opposite: one more project in progress means everyone gets spread a little thinner.
Pipelining means releasing new projects based on the capacity of the most constrained resource, not on the date they were approved. Fewer projects run at once, each one gets real focus, and more projects finish over the year. That's the logic behind Realization's Focus & Finish approach.
These results come from Realization customers running many projects on shared resources, as they reported them.
Organization
Before
After
Dr. Reddy's Laboratories (pharmaceutical new product development)
6 projects completed per quarter, 20% on time
11 projects completed per quarter, 80% on time
Amdocs (customized software for telecoms)
8 projects in crisis needing CEO-level attention
20% shorter cycle time; no projects in crisis the following year
ThyssenKrupp (automotive assembly systems)
70% of projects late, high overtime
Lateness down 50%; 15% more projects completed
"The first thing we saw is that per project, we can shorten the timeline by 20%. We are finishing this year without a crisis in any of our projects."
Shalom Passy, Executive VP, Amdocs
See all customer resultsGeneral project management tools are good at what they do: tasks, boards, timelines, collaboration. Many teams should keep using them. The difference is what they are built to solve.
Question
General project management tools
Concerto (Critical Chain)
What does the schedule account for?
Tasks and dates, project by project
Tasks, dates and shared resources across all projects
How are priorities set?
By the person or project asking
By buffer status across the portfolio
When do new projects start?
When they're approved
When there's capacity to work on them
Where does safety time sit?
Inside each task estimate
In shared project buffers
What do managers review?
Status updates and task dates
Buffer status: green, yellow, red
If your projects rarely share people, a general tool may be all you need. If they do, the schedule has to see the whole portfolio.
See how Concerto worksMulti-project management is the planning and control of many projects that share the same people, equipment and budget. It sets priorities and start dates across the whole portfolio, so shared resources aren't overloaded.
Multi-project management software schedules many projects against a shared pool of resources and shows where they compete. Critical Chain software such as Concerto also limits work in process and sets priorities by buffer status.
When people switch between several projects, every task takes longer, and every project waits for every other one. Finishing one task before starting the next gets all projects done sooner.
Portfolio management decides which projects to do. Multi-project management decides how and when to run them on shared resources. Critical Chain connects the two by releasing approved projects based on capacity.
Common signs: people assigned to several projects at once, priorities that change every week, many projects started but few finishing, and one team or piece of equipment that everyone waits for.