Critical Chain Buffers: Project, Feeding and Resource Buffers Explained

Critical chain buffers explained: the project, feeding and resource buffers, how to size them, and how the fever chart tells managers when to act.

A buffer in critical chain project management is a pooled block of time that protects a project's completion date against waiting and uncertainty. Critical chain buffers are built from the allowances that conventional plans hide inside every task estimate. Critical chain project management (CCPM) uses three buffers: the project buffer at the end of the critical chain, feeding buffers where side chains join the critical chain, and resource buffers that warn scarce people or equipment before they are needed. Eliyahu Goldratt introduced the buffers in his 1997 book Critical Chain. Managers then run the project by buffer consumption: they compare how much buffer has been used with how much of the critical chain is finished. Realization built this buffer management into Concerto, the multi-project software it developed with Goldratt, and Realization customers including the US Navy depots and Boeing manage their projects by buffer status.

What is a buffer in project management?

A buffer in project management is time set aside to absorb delays, so that one late task does not move the delivery date. Conventional plans spread that time across every task as padding. Critical chain moves it out of the tasks and into a few shared buffers placed where they protect the plan.

The reason is simple. Nobody can predict which task will wait for a part, a decision or a person. When the allowance sits inside each task, it gets used up whether the task needed it or not. People start late because the estimate looks comfortable, which Goldratt called the student syndrome. Work expands to fill the time available, which is Parkinson's law. Early finishes are rarely reported, so they never help the project. Delays add up and gains disappear.

A pooled buffer works the other way. Delays draw on it where they actually happen, and early finishes put time back into it.

The three critical chain buffers

Critical chain uses three buffers, and each one protects a different part of the plan.

  1. The project buffer sits at the end of the critical chain and protects the delivery date. It is the main buffer and the one managers watch every day.
  2. A feeding buffer sits where a non-critical chain of tasks joins the critical chain. It stops a delay on the side chain from holding up the critical chain.
  3. A resource buffer is an alert, not a block of time. It tells a scarce resource, such as a test team or a hangar crew, that critical chain work is coming, so they are ready when it arrives.

The project buffer and feeding buffers add time to the schedule. The resource buffer adds none. It only changes when people know what is coming next.

Project buffer

The project buffer is a time buffer placed at the end of the critical chain to protect the project's completion date. Its size comes from the allowances removed from the tasks on the critical chain. Because one shared buffer covers the whole chain, it can be smaller than the sum of all the padding it replaces, so the committed date often gets earlier, not later.

Feeding buffer

The feeding buffer is a time buffer placed at the end of a feeding chain, just before it merges into the critical chain. A feeding chain is any sequence of tasks that is not on the critical chain but supplies it, such as procurement of a long-lead part that must arrive before assembly. If the part is late, the feeding buffer absorbs the delay first. The critical chain only feels it once the feeding buffer is used up.

Resource buffer

The resource buffer is a warning placed ahead of a critical chain task that needs a scarce resource. It typically fires a set number of days before the task can start. Resource buffers matter most where specialists are shared across projects. They prevent the most common critical chain delay: the work is ready, but the person is still busy on something else.

How to size critical chain buffers

Critical chain buffers are sized with one of two common methods: the cut and paste method or the root square error method. Both start from the same step. Each task gets two estimates: a safe estimate with the usual allowance included, and a focused estimate for the work alone.

The cut and paste method (the 50% rule)

The cut and paste method sets each task to roughly half its safe estimate, then sizes the project buffer at 50% of the resulting critical chain. Goldratt used this rule of thumb in Critical Chain. Feeding buffers follow the same rule: 50% of the feeding chain they protect.

A short example shows the arithmetic. A critical chain of five tasks has safe estimates that add up to 80 days. Cut each task to half, and the chain becomes 40 days. The project buffer is 50% of 40, so 20 days. The plan commits to 60 days instead of 80, and the 20-day buffer protects it.

The method is easy to explain and easy to audit. Its weakness shows up on long chains, where 50% can be more buffer than the project needs, and on very short chains, where it can be too little.

The root square error method

The root square error method sizes a buffer from the uncertainty in each task rather than from the chain's total length. For each task on the chain, take the difference between the safe and focused estimates, square it, add the squares together, and take the square root. The Product Development Institute described this approach in 1999, and Larry Leach covers it in his book Critical Chain Project Management.

Using the same five tasks, suppose the differences between safe and focused estimates are 8, 8, 8, 8 and 8 days. The squares add up to 320. The square root of 320 is about 18 days. The buffer comes out slightly smaller than the 20 days from the 50% rule, and the gap grows as the chain gets longer.

Root square error rewards honest estimates. A task with a lot of uncertainty adds a lot to the buffer. A routine task adds very little.

Which sizing method to use

The cut and paste method is the better starting point for teams new to critical chain, because everyone can check it in their head. The root square error method suits organizations with enough history to give each task a realistic range. In practice, the exact size matters less than people expect. A buffer that is watched every day and acted on protects a project far better than a precisely calculated buffer that nobody looks at.

Buffer consumption and the fever chart

Buffer consumption is the share of a buffer that delays have used up so far. On its own it says little, because 40% consumed is fine near the end of a project and alarming near the start. Critical chain therefore compares buffer consumption with progress along the critical chain.

The fever chart plots that comparison. The horizontal axis shows the percentage of the critical chain completed. The vertical axis shows the percentage of the project buffer consumed. Each project is a point, and the line it traces over the weeks shows whether it is getting healthier or sicker.

A project that has completed 50% of its critical chain and used 30% of its buffer is in good shape. A project that has completed 20% of its chain and used 60% of its buffer needs attention now, long before any milestone is missed.

Green, yellow and red: what managers do at each zone

The fever chart divides into three zones, and each zone tells managers what to do.

  • Green means the project has used less buffer than its progress justifies. Managers leave it alone and let the team work.
  • Yellow means buffer use is getting ahead of progress. Managers plan a recovery action but do not act on it yet.
  • Red means the completion date is at risk. Managers carry out the recovery plan, which can mean moving resources, removing a blocker or escalating a decision.

The zones replace dozens of status reports with one question: which projects are in the red? Executives spend their time on those few projects, and the rest are left to run.

Buffer status also sets priorities for the people doing the work. When two tasks compete for the same person, the task protecting the project with the most consumed buffer goes first. That gives every person one task list, ranked the same way across all projects.

Buffer management across many projects

Buffer management across a portfolio works the same way, with one fever chart for all projects. Each project keeps its own project buffer, and managers compare buffer status across projects to decide where shared resources go next.

This is where buffers and staggering work together. Buffers protect each project against waiting and uncertainty. Staggering limits how many projects compete for the same resources at once. If too many projects start together, every buffer turns red at the same time and the chart stops being useful. Our project portfolio management page explains how staggering keeps that from happening.

What buffer management looks like in practice

Realization customers describe the change in their own words. These quotes come from their published case studies.

"So now we put our priorities based upon the relation to the critical chain. If a task is not on the critical chain and it happens to be late to baseline, that's okay, right? We want to put our emphasis on our critical chain activities."
John Weisinger, Boeing Satellite Development Center

The Boeing team measured results by the percentage of buffer consumed along the critical chain and the feeding chains, reviewed daily on a performance board and weekly in a schedule review. One unit-level design project finished in 70% of its planned time.

"We had lost that ability to buffer. The solution was clear... a radical change in approach."
John Laughter, Sr. VP, Delta TechOps

At Vardhman Special Steels, Concerto flagged a risk to the expansion project's completion nearly seven months in advance. That early warning gave the team time to set up joint reviews with the equipment manufacturer, and the project finished in eleven months against an expected twelve and a half.

Buffer management in maintenance, repair and overhaul

Buffer management in maintenance, repair and overhaul (MRO) protects aircraft or ship delivery dates against the biggest source of uncertainty in the work: what the inspectors find once the panels come off. A depot cannot know in advance how much repair an airframe needs. It can, however, pool that uncertainty in a buffer and watch it.

At the US Navy's F/A-18 depots, Realization helped move management "from backward looking reports to forward-looking delay and bottleneck alerts," in the words of Realization CEO Sanjeev Gupta. Within a year, depot throughput rose by 40%, and the Fleet Readiness Center Southeast cut work in progress from 36 aircraft to 17.

Frequently asked questions

What is a buffer in project management?

A buffer in project management is time set aside to absorb delays so that the delivery date holds. In critical chain project management, buffers are pooled from the allowances removed from individual task estimates and placed at the end of the project or where side chains join the critical chain.

What are the three buffers in critical chain?

The three critical chain buffers are the project buffer, the feeding buffer and the resource buffer. The project buffer protects the delivery date, feeding buffers protect the critical chain from delays on side chains, and resource buffers are alerts that get scarce resources ready in time.

What is an example of a critical chain buffer?

A critical chain of five tasks with safe estimates of 80 days is cut to 40 days of focused work, and a 20-day project buffer is added at the end. The project commits to 60 days, and delays on any of the five tasks draw on the shared 20 days.

How big should a project buffer be?

A project buffer is usually 50% of the critical chain under the cut and paste method. The root square error method gives a smaller buffer on long chains, because it sizes the buffer from each task's uncertainty instead of the chain's total length.

What is a fever chart in CCPM?

A fever chart in CCPM plots the percentage of project buffer consumed against the percentage of the critical chain completed. Green, yellow and red zones on the chart show whether a project needs no action, a recovery plan or immediate intervention.

What is the critical chain method in project management?

The critical chain method is a way of planning and running projects that schedules around resource availability as well as task dependencies, and protects completion with shared buffers instead of padding in every task. Eliyahu Goldratt introduced it in 1997.

For the full method, from buffering to staggering, read our Critical Chain Project Management guide, or see how buffer status drives daily priorities in Concerto.