Critical Chain project management software. Built with the man who invented Critical Chain.
Concerto is CCPM software that schedules every project in your organization against the people and equipment they share. Instead of padding each task, it pools safety time into a project buffer and tracks how fast that buffer is being used. Each team member gets one list: what to work on next. Managers see which projects are at risk while there is still time to act. Realization built Concerto in the late 1990s with Dr. Eliyahu Goldratt, the author of Critical Chain. Our customers report 25 to 50% shorter project timelines and 20 to 30% more throughput, often within 90 days.
They're late because everyone is working on everything at once.
A typical organization starts projects as early as it can, keeps every resource 100% busy and pads every task estimate to be safe. It feels responsible. It produces the opposite: people jump between five projects, the padding gets used up by late starts and switching, and the critical work waits in a queue behind work that could have waited.
To solve traffic jams, you don't add more cars to the road. Concerto takes cars off the road.
Concerto follows the Critical Chain method in five steps.
Step
What Concerto does
What changes for your teams
1. Focused durations
Cuts task estimates to the time the work takes without interruptions
Tasks stop expanding to fill the padding
2. Project buffer
Moves the safety time to the end of the project
The buffer protects the delivery date, not individual tasks
3. Critical chain
Finds the longest chain of tasks once both dependencies and resource availability count
No plan assumes a specialist is free when they aren't
4. Buffer tracking
Compares buffer used with work completed on every project
Managers act on real risk, early
5. Task priorities
Gives each person a ranked list of what to work on next
No more arguing about which project comes first
The difference from the critical path is step 3. The critical path ignores whether the people are available. The critical chain does not.
Scheduling one project well is the easy part. The real gains show up when every project sits on one schedule.
Concerto puts your whole portfolio on a single schedule, against the same engineers, mechanics, test rigs and hangar bays. New projects are released only when there's capacity to do them. The resource that limits the whole organization becomes visible, so you schedule everything around it. And when a customer asks for a date, you can give one based on actual capacity.
In 1999 Realization became the first company to bring multi-project, web-based scheduling to the world of projects. For the first time, an entire organization could work from one shared schedule in real time. That idea still drives Concerto today.
These results come from Realization customers, in their own words. They are what those organizations reported, not a promise.
"We had a 20% increase in just capacity alone. A 23% increase in engine production."
Gregory Mayes, General Manager, Delta Airlines
"We were able to see an 18% reduction in our cycle time. From a projected 17-month effort to finishing in 14 months."
Steven Pryor, Director, Spirit AeroSystems
"The first thing we saw is that per project, we can shorten the timeline by 20%."
Shalom Passy, Executive VP, Amdocs
Organization
Before
After
US Navy, Fleet Readiness Center Southeast (F-18)
6 aircraft a year, 36 in work
11 aircraft a year, 17 in work
Airbus Defence and Space
24 drawings a week, 41% engineering cost overrun
32 drawings a week, 6% overrun
ABB Cordoba
8-month engineering cycle, 85% on time
3-month cycle, 95% on time
BHP Billiton
Historical 2-week delays, 20% man-hour overruns
Finished 3 weeks early with 25% fewer man-hours
Concerto is used by organizations that run many projects on shared resources. Realization has worked with more than 350 organizations, including more than 25 aircraft MROs.
Aircraft, engine, ship and vehicle depots, where every extra day in the shop is a day the asset can't fly or sail. The Navy's F/A-18 depot increased throughput by 40% in its first year.
Design offices and R&D teams where projects compete for the same specialists and test capacity. Airbus Defence and Space raised design throughput by 33%.
Plants, shipyards and capital projects with fixed dates and many contractors. BHP Billiton finished an iron ore development project three weeks early.
It started with a book.
In 1991 our founder, Sanjeev Gupta, read The Goal by Eliyahu Goldratt and used its ideas to turn around a bottlenecked Xerox plant. In 1997 Goldratt sent Sanjeev the galleys of his next novel, Critical Chain, and the two talked about how software could make its ideas work in practice. When an aerospace and defense company asked Goldratt to help it run projects the Critical Chain way, he called Sanjeev. That project became Concerto.
Read our storySoftware on its own doesn't change how projects run. People do. So every Concerto rollout comes with Realization's implementation team.
1. We map your projects, your shared resources and your current bottleneck.
2. We load your projects into Concerto, set focused durations and buffers, and agree on how much work runs at once.
3. We train project managers, resource managers and team members to work from task priorities and buffer status.
4. We run weekly buffer reviews with you until the new way of working sticks.
Most customers see results within 90 days. The Navy's depots took about four months to get the plan moving.
CCPM software is project scheduling software that uses Critical Chain Project Management. It plans around resource availability, moves safety time into shared buffers and tracks buffer use to show which projects need attention.
The critical chain is the longest sequence of dependent tasks once resource limits are included. The method protects that chain with one project buffer instead of padding each task, and limits how many projects run at the same time.
Concerto is for any organization where several projects compete for the same people or equipment. That can be a single maintenance depot or an enterprise portfolio of hundreds of projects.
Some tools offer free trials or basic Critical Chain features. Organizations running many projects at once usually need multi-project scheduling, buffer management and help changing how teams work. That combination is what Concerto and Realization provide.
Realization customers often see results within 90 days.
If your goal is to finish far more projects, far faster, with the people you already have, let's talk.