A critical chain scheduling example starts from a normal project plan and turns it into a resource-feasible schedule protected by buffers. To create a critical chain schedule, cut each task estimate to a focused duration, resolve resource conflicts so no person is double-booked, and identify the longest chain of task and resource dependencies. Then add a project buffer at the end of the critical chain and feeding buffers where side chains join it. The example below uses six tasks and one shared engineer. It shows the step most guides skip: how a single resource conflict turns a 36-day critical path into a different critical chain. The finished schedule commits to 39 days. The same plan with padded estimates and the conflict resolved would need 52.
The example project
The example project builds and qualifies a new test fixture. It has six tasks, three people and the usual safe estimates.
- Task A, write the specification: Ana, the engineer, 10 days.
- Task B, design the fixture: Ana, 16 days, after Task A.
- Task E, write the test procedure: Ana, 16 days, after Task A.
- Task C, order parts: the buyer, 12 days.
- Task D, build the frame: Tom, the technician, 12 days, after Task C.
- Task F, run the qualification test: Tom, 10 days, after Tasks B, D and E are all done.
The critical path method looks only at task logic. Two paths tie for longest: A, B, F and A, E, F, each 10 + 16 + 10 = 36 days. The plan promises 36 days.
The plan cannot keep that promise. Tasks B and E both need Ana at the same time.
Step 1: cut estimates to focused durations
The first step in a critical chain schedule is to separate the work from the allowances for waiting and uncertainty. Each estimate above includes safety time. A focused duration is the time the task takes when the person works on it without interruption, and the cut and paste rule sets it at roughly half the safe estimate.
- Task A: 5 days. Task B: 8 days. Task E: 8 days.
- Task C: 6 days. Task D: 6 days. Task F: 5 days.
The safety time does not disappear. It moves into buffers in steps 4 and 5.
Step 2: resolve resource conflicts
The second step is to make sure nobody is scheduled on two tasks at once. Ana has three tasks: A, B and E. Task A comes first. Tasks B and E can both start after A, but Ana can only do one at a time, so they go in sequence.
Ana's sequence becomes A, B, E: days 0 to 5, 5 to 13, and 13 to 21. Task F starts on day 21, when Ana's last task is done, and finishes on day 26.
This step is resource leveling, and it is where critical chain and critical path part ways. The critical path schedule assumed Ana could do two things at once. Most project plans make this assumption somewhere, and most late projects pay for it.
Step 3: find the critical chain
The critical chain is the longest sequence of tasks once both task and resource dependencies are counted. In this example, it is A, B, E, F: 5 + 8 + 8 + 5 = 26 days of focused work.
Task E is on the critical chain even though it was never on the critical path in its own right. It is there because it shares Ana with Task B. That is the defining feature of a critical chain: resource dependencies count as much as task dependencies.
Tasks C and D are not on the critical chain. They form a feeding chain of 6 + 6 = 12 days that joins the critical chain at Task F.
Step 4: add the project buffer
The project buffer goes at the end of the critical chain and protects the completion date. Using the 50% rule, the project buffer is half of 26, so 13 days.
The project now commits to 26 + 13 = 39 days. Compare that with the alternatives:
- The critical path plan promised 36 days, but it ignored the conflict over Ana and could not be delivered.
- The padded plan with the conflict resolved needs 10 + 16 + 16 + 10 = 52 days.
- The critical chain plan commits to 39 days, and 13 of them are buffer that every task on the chain can draw on.
Step 5: add feeding buffers
A feeding buffer goes at the end of each feeding chain, just before it joins the critical chain. The feeding chain C, D is 12 days long, so its feeding buffer is 50% of 12, which is 6 days.
Task F starts on day 21, so the feeding chain and its buffer must finish by then. Working backwards, the feeding buffer runs from day 15 to 21, Task D from day 9 to 15, and Task C from day 3 to 9. Ordering parts on day 3 rather than day 0 looks odd, but it keeps money and attention free until they are needed. If parts arrive late, the 6-day feeding buffer absorbs it before Task F feels anything.
A resource buffer can also go in front of Task F. It is an alert that tells Tom, a few days ahead, that the test is coming, so he is not halfway through another job when Task F is ready to start.
Step 6: run it with buffer management
Once work starts, the team manages the project by comparing buffer consumption with progress on the critical chain. Nobody tracks whether Task B finished on its exact date.
Suppose Task B takes 11 days instead of 8. The project buffer drops from 13 days to 10, so 23% of it is used, while half of the critical chain is complete. The project is in the green, and nobody needs to react.
Suppose instead the procedure in Task E runs into trouble and takes 15 days. Now 7 of the 13 buffer days are gone, 54% of the buffer, with about 81% of the chain complete. The project is still green, because progress is ahead of buffer use. Had the same 7 days been lost during Task A, with less than 20% of the chain done, the project would be in the red, and the team would act at once, for example by getting Tom involved in test preparation early.
This is the fever chart in practice. The critical chain buffers article explains the green, yellow and red zones in detail.
What changes with many projects
In a real organization, Ana is not working on one test fixture. She is shared across several projects, and so is Tom. The same steps apply, with one more decision on top: when each project is allowed to start.
If every project starts at once, Ana's queue grows, every critical chain gets longer and every buffer turns red together. Critical chain answers this with staggering: projects are released according to the capacity of the most loaded resource. Our project portfolio management page covers staggering in detail. This is also the point where spreadsheets stop working and organizations move to software such as Concerto, which keeps every project's schedule and buffers current across shared resources.
A real example: a design project in 70% of the time
Realization customers have run this method on real projects. At Boeing's Satellite Development Center, the team first tried critical chain on a difficult follow-on unit. They put priorities on critical chain tasks, reviewed buffer consumption daily and weekly, and finished the unit-level design project in 70% of its planned time.
"This gave us the leverage to go out to the rest of the organization and tell them that we took one of our toughest units, we used this new approach called CCPM, and it worked."
John Weisinger, Boeing Satellite Development Center
Frequently asked questions
How do you create a critical chain schedule?
To create a critical chain schedule, cut each task estimate to a focused duration, resolve resource conflicts and identify the longest chain of task and resource dependencies. Then add a project buffer at the end and feeding buffers where side chains join the critical chain.
What is the critical chain method in project management?
The critical chain method is a way of planning and running projects that schedules around resource availability as well as task dependencies, and protects completion with shared buffers instead of padding in every task. Eliyahu Goldratt introduced it in his 1997 book Critical Chain.
What is an example of a critical chain?
In a project where one engineer must design a fixture and write its test procedure, both tasks end up on the critical chain because they share the engineer. The critical path would show them as parallel and promise an earlier date than the engineer can deliver.
How is the critical chain different from the critical path in an example?
In this example, the critical path promises 36 days because it assumes the engineer can work on two tasks at once. The critical chain resolves that conflict first and commits to 39 days, including a 13-day project buffer.
Why are task estimates cut in half in critical chain?
Task estimates are cut so that the allowance for waiting and uncertainty sits in a shared buffer instead of inside each task. Half is a rule of thumb from Goldratt, and teams adjust it once they have their own history.
Read the full Critical Chain Project Management guide for the principles behind each step.